Installation & Commissioning

Half of a system’s performance depends on installation. Eight steps, each checked and recorded.

Submit a service request
01

Eight steps

Once the collector, ductwork, fan and controls are installed, commissioning brings the system to its design performance. SCALES provides interface documents, installation guidance and commissioning; who installs and who commissions is written into the contract. Whatever the split, all eight steps are completed.

StepWhat happensWhoNeededRecord
1 Interface confirmationConfirm location and size of foundations, inlet and outlet, power, compressed air, water (wet units), dust and liquid dischargeSCALES supplies interface data; customer and contractor confirmGeneral arrangement, interface list, shop layoutSigned interface list
2 Site preparationFoundation and load capacity, lifting route, service space, power and air brought to the unitCustomer or contractorFoundation drawing, lifting planSite acceptance record
3 Delivery checkCheck main unit, filters, control panel, accessories and documents against the packing list; check for transport damageCustomer and installer; SCALES on site or remotelyPacking list, contract equipment listDelivery acceptance, list of missing or damaged items
4 Mechanical installationPosition, level and fix the unit; connect ducts, flanges and supports; water and sludge lines for wet units; oil drains for mist unitsInstallerInstallation manual, duct drawingInstallation checklist
5 Electrical and controlsMain supply, earthing, fan motor, pulse control, differential-pressure gauge, VFD, interlocks and alarmsQualified electriciansSchematics, wiring diagramsElectrical check and earthing test records
6 Pre-start checkCheck rotation, fasteners, damper positions, filter fitting, seals, air pressure, water level; remove debrisSCALES commissioning engineer with the customerPre-start checklistSigned checklist
7 Trial run and adjustmentRun unloaded and loaded; balance branch dampers; set pulse-cleaning parameters; record current, pressure, pressure drop, cleaning and noiseSCALES commissioning engineerDesign airflow, process conditionsCommissioning record, parameter settings
8 Acceptance and handoverAccept against the contract; hand over manuals, drawings, commissioning records and spares list; arrange trainingBoth partiesContract acceptance termsAcceptance certificate, handover document list
02

What we check during commissioning

Airflow and pressure
Hood velocity at the main capture points, branch balance, and whether the fan runs within its design range.
Filtration and cleaning
Initial pressure drop, pulse-valve action and stable air pressure (SCU pulse valves work from 0.2 to 0.6 MPa).
Dust and liquid discharge
Rotary valves, dust drawers, oil drains, and recirculation water and scrapers on wet units.
Electrical and safety
Rotation, current, overload protection, emergency stop, door interlocks and alarms.
Results at the station
Whether fume and dust are captured at the station, with no visible escape.
03

Common installation problems

  • Too many or too tight bends: pressure loss exceeds the fan and the far end gets no air.
  • Wet or oily compressed air damages pulse valves and cartridges; fit a dryer and filter at the supply.
  • Not enough space at access doors and on the filter-change side makes maintenance hard.
  • A fan running backwards delivers only a fraction of the design airflow.
  • Poor earthing, which is especially dangerous with combustible dust and electrostatic units.
04

Safety and early planning

Installation and commissioning involve work at height, lifting, hot work and live electrical work; obtain site permits. Before working inside the unit, isolate power, lock out and tag, release compressed air and make sure the fan has stopped.

At quotation stage, send the shop layout, proposed unit location, lifting conditions, and power and air supply. Our proposal then covers service space, filter-change route and lifting.