SERVICE SUPPORT
Installation & Commissioning
Half of a system’s performance depends on installation. Eight steps, each checked and recorded.
Submit a service requestEight steps
Once the collector, ductwork, fan and controls are installed, commissioning brings the system to its design performance. SCALES provides interface documents, installation guidance and commissioning; who installs and who commissions is written into the contract. Whatever the split, all eight steps are completed.
| Step | What happens | Who | Needed | Record |
|---|---|---|---|---|
| 1 Interface confirmation | Confirm location and size of foundations, inlet and outlet, power, compressed air, water (wet units), dust and liquid discharge | SCALES supplies interface data; customer and contractor confirm | General arrangement, interface list, shop layout | Signed interface list |
| 2 Site preparation | Foundation and load capacity, lifting route, service space, power and air brought to the unit | Customer or contractor | Foundation drawing, lifting plan | Site acceptance record |
| 3 Delivery check | Check main unit, filters, control panel, accessories and documents against the packing list; check for transport damage | Customer and installer; SCALES on site or remotely | Packing list, contract equipment list | Delivery acceptance, list of missing or damaged items |
| 4 Mechanical installation | Position, level and fix the unit; connect ducts, flanges and supports; water and sludge lines for wet units; oil drains for mist units | Installer | Installation manual, duct drawing | Installation checklist |
| 5 Electrical and controls | Main supply, earthing, fan motor, pulse control, differential-pressure gauge, VFD, interlocks and alarms | Qualified electricians | Schematics, wiring diagrams | Electrical check and earthing test records |
| 6 Pre-start check | Check rotation, fasteners, damper positions, filter fitting, seals, air pressure, water level; remove debris | SCALES commissioning engineer with the customer | Pre-start checklist | Signed checklist |
| 7 Trial run and adjustment | Run unloaded and loaded; balance branch dampers; set pulse-cleaning parameters; record current, pressure, pressure drop, cleaning and noise | SCALES commissioning engineer | Design airflow, process conditions | Commissioning record, parameter settings |
| 8 Acceptance and handover | Accept against the contract; hand over manuals, drawings, commissioning records and spares list; arrange training | Both parties | Contract acceptance terms | Acceptance certificate, handover document list |
What we check during commissioning
- Airflow and pressure
- Hood velocity at the main capture points, branch balance, and whether the fan runs within its design range.
- Filtration and cleaning
- Initial pressure drop, pulse-valve action and stable air pressure (SCU pulse valves work from 0.2 to 0.6 MPa).
- Dust and liquid discharge
- Rotary valves, dust drawers, oil drains, and recirculation water and scrapers on wet units.
- Electrical and safety
- Rotation, current, overload protection, emergency stop, door interlocks and alarms.
- Results at the station
- Whether fume and dust are captured at the station, with no visible escape.
Common installation problems
- Too many or too tight bends: pressure loss exceeds the fan and the far end gets no air.
- Wet or oily compressed air damages pulse valves and cartridges; fit a dryer and filter at the supply.
- Not enough space at access doors and on the filter-change side makes maintenance hard.
- A fan running backwards delivers only a fraction of the design airflow.
- Poor earthing, which is especially dangerous with combustible dust and electrostatic units.
Safety and early planning
Installation and commissioning involve work at height, lifting, hot work and live electrical work; obtain site permits. Before working inside the unit, isolate power, lock out and tag, release compressed air and make sure the fan has stopped.
At quotation stage, send the shop layout, proposed unit location, lifting conditions, and power and air supply. Our proposal then covers service space, filter-change route and lifting.