REFERENCE PROJECT · Lithium Batteries & New-Energy Materials
Dongguan, Guangdong · Oil fume from separator production
- Airflow
- 20,000 m³/h
- Completed
- 2020
- System
- Two-stage electrostatic system
Project facts
This project treats oil fume from separator production with a two-stage electrostatic system. Design airflow is 20,000 m³/h; the system was completed in 2020.
| Location | Dongguan, Guangdong |
|---|---|
| Industry | Lithium Batteries & New-Energy Materials |
| Process | Oil fume from separator production |
| Airflow | 20,000 m³/h |
| System route | Two-stage electrostatic system |
| Completed | 2020 |
| Project no. | C16 |